    Pearl Harbor’s Dry Dock 5, the first built for the Navy’s newest submarines, nears dewatering

    The Vanguard USA DeskBy The Vanguard USA Desk9 October 2026Updated:26 October 20264 Mins Read
    Share Facebook Twitter Pinterest LinkedIn Tumblr Reddit Telegram Email
    A dark attack submarine floats in a flooded concrete dry dock at a shipyard, with a ship and hills in the background.
    Photo: U.S. Navy/Machinist's Mate 3rd Class Dustan Longhini (public domain)
    Share
    Facebook Twitter LinkedIn Pinterest Email

    The Navy’s new Dry Dock 5 at Pearl Harbor Naval Shipyard is approaching its next major milestone, the draining of a temporary enclosure in the harbor so crews can build the dock’s permanent walls, according to a Navy article published Oct. 8 by the Officer in Charge of Construction Pearl Harbor Naval Shipyard.

    The facility, military construction project P-209, replaces Dry Dock 3, which was built during World War II. “Because Dry Dock 3 is too shallow for newer, larger Virginia-class attack submarines, Dry Dock 5 will be the first dry dock built specifically for the latest nuclear submarines,” said Capt. Ryan McCrillis, commander of Pearl Harbor Naval Shipyard & Intermediate Maintenance Facility. He said it is designed to add another century of maintenance capability.

    P-209 is being delivered through the Navy’s Shipyard Infrastructure Optimization Program, which Mark Edelson, program executive officer for Infrastructure and Expeditionary, described as “a comprehensive, long-term recapitalization effort” at the Navy’s four public shipyards. The Navy article does not give a total cost or a completion date for Dry Dock 5.

    Building a dry dock beneath the water

    Preparing the site meant reshaping it above and below the water. Crews dredged sediment from the harbor floor, created laydown and fabrication areas on the nearby Waipio Peninsula and built a temporary trestle, a bridge-like work platform over the water, to move workers, equipment and large components.

    To create a dry work area inside the harbor, crews are driving large steel pipe piles alongside interlocking steel sheet piles to form a cofferdam. They build the perimeter downward in stages, driving one pile section, welding another on top and driving again until it reaches the required depth. Braces and struts connect the parallel walls to help them resist the pressure of the surrounding water.

    See also  Army cavalry commander outlines cheap drones and decoy robots to fool enemy sensors at the breach

    The dock floor started on land. Crews built nine prefabricated concrete floor units at Waipio Peninsula, moved each one by water and lowered it onto the harbor floor. Divers and concrete plant operators then placed concrete underwater through tremie pipes to connect the units to the surrounding foundation. Beside the cofferdam, crews are also building the pump well that will drain the dock during future maintenance.

    Illustration of a steel cofferdam in a harbor with prefabricated floor units, bracing struts, a red crane and a submarine
    Illustration: The Vanguard USA (AI-generated)

    Dewatering is the riskiest step

    The next major transition is dewatering, pumping the water out of the cofferdam to expose the foundation and create a dry workspace for the permanent walls. “The ongoing preparations for dewatering are the most important and dangerous part of the project,” said Capt. Chris Coggins, commanding officer of the construction office. “Without completing this phase, workers will not be able to safely enter or build at a depth of 60 feet below the adjacent waterline.”

    Coggins said the perimeter pile driving must first be completed and inspected. “This provides the bathtub and door to safely keep the water out,” he said. Beyond the dock itself, P-209 includes utility systems, crane-rail foundations, pump stations, a water treatment system, an electrical substation and 10 supporting buildings.

    A workforce set to grow past 1,000

    The construction workforce is expected to grow from about 350 workers per day to more than 1,000 as the project enters its next phase, increasing demand for skilled labor, concrete and other locally supplied materials in Hawaii. Coggins said teamwork with local unions and batch plant operators to prioritize supplies will be key.

    See also  USS Arleigh Burke enters dry dock in Spain as the Navy expands forward-deployed maintenance in Europe

    The construction office, which reports to Naval Facilities Engineering Systems Command Pacific, manages the build, and the shipyard will operate the dock once it is complete and certified. McCrillis said shipyard employees are already involved in design, testing and planning so the yard can begin maintaining submarines when the dock is finished, and that its apprenticeship program takes on about 150 new employees each year.

    Related coverage: Army and Navy labs keep base camp shelter systems running at minus 65 F in cold chamber tests

    Dry Dock 5 NAVFAC Pacific Pearl Harbor Naval Shipyard shipbuilding SIOP U.S. Navy Virginia-class submarine
    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Previous ArticleAtomic Machines emerges from stealth with $250 million and a fast switch for AI data centers
    Next Article Pentagon and Lockheed finalize a 10-year F-35 framework for at least 850 jets, pending Congress
    The Vanguard USA Desk

    The Vanguard USA Desk is the editorial team of The Vanguard USA, published by EDGENICHE. It reports on U.S. defense technology, space, deep tech and AI, and the industrial base and energy systems behind them.

    Related Posts

    Defense

    Air Force and Northrop Grumman say the B-21 Raider released its first weapon in a test from Edwards Air Force Base

    14 November 2026
    Defense

    CENTCOM says U.S. forces shot down two Iranian drones headed for Bahrain, denying IRGC claim of a radar strike

    13 November 2026
    Defense

    Navy relieved USS South Dakota’s command triad without notifying Congress, top House Armed Services Democrats say

    13 November 2026
    Top stories

    NRC pushes its review of Orano’s Project Ike uranium enrichment plant in Oak Ridge to June 2027, Nuclear News reports

    14 November 2026

    Office of Space Commerce picks Starcloud, Portal, Cowboy Space and Redwire’s SpaceMD for its certification pilot

    14 November 2026

    Commerce Department finalizes a CHIPS Act R&D award of up to $100 million to quantum computing firm Atom Computing

    14 November 2026

    SpaceX catches Starship’s Ship 42 with its launch tower after 14 orbits on Flight 15, a first for an orbital upper stage

    14 November 2026
    © 2026 The Vanguard USA

    Type above and press Enter to search. Press Esc to cancel.